The SAP S/4HANA Production Planning and Manufacturing Certification Sample Question Set is prepared to make you familiar with actual SAP C_TS422_2021, C_TS422_2020 exam question format and exam pattern. To get familiar with more exam properties, we suggest you to try our Sample SAP S/4HANA Production Planning and Manufacturing Certification Practice Exam.
This Sample SAP S/4HANA Production Planning and Manufacturing Certification Practice Exam is designed for evaluation purpose only. If you are planning to write the SAP S/4HANA Production Planning and Manufacturing Certification Exam (C_TS422_2021, C_TS422_2020) and really want to test your SAP S/4HANA Production Planning and Manufacturing subject knowledge to identify your weak areas, we strongly recommend you to start your preparation with our Premium SAP S/4HANA Production Planning and Manufacturing Certification Practice Exam.
SAP S/4HANA Production Planning and Manufacturing Sample Questions:
01. What generates capacity requirements in a process order?
Please choose the correct answer.
a) Activities
b) Phases
c) Operations
d) Resources
02. You run MRP for a material that was planned using Demand-Driven Replenishment. Towards which buffer level does the MRP run create a replenishment proposal?
Please choose the correct answer.
a) Top of Green
b) Top of Red
c) Top of Yellow
d) Top of Red Base
03. Which material master data can you copy when you use the Copy Material program (transaction MMCC, Material Master Copier) to create new materials?
There are 2 correct answers to this question.
a) Storage location data
b) Warehouse number data
c) MRP area data
d) Production version data
04. A material in your company is planned with planning strategy 70 (Planning at assembly level).
The consumption mode has been set to backwards with a consumption period of 12 days. Starting from when are the 12 days counted backwards?
Please choose the correct answer.
a) From the planned independent requirement date of the material
b) From the requested delivery date of the related finished good
c) From the availability date of the related finished good
d) From the dependent requirement date of the material
05. Which of the following elements does the MRP run take into account?
There are 2 correct answers to this question.
a) Sales orders
b) Planned independent requirements
c) Shipments
d) Material documents
06. You are creating a production order manually. What activities are involved in this process?
There are 3 correct answers to this question.
a) Planning selection
b) Master data selection
c) Capacity requirements determination
d) Order type determination
e) Actual cost calculation
07. What are the three layers in the SAP Best Practices Content for SAP S/4HANA?
There are 3 correct answers to this question.
a) Solution Package
b) Scope Items
c) Building Blocks
d) Test Scripts
e) Process Flows
08. Advanced Planning is delivered with standard out-of-the-box order and resource evaluations. Which evaluations are available?
There are 2 correct answers to this question.
a) Resource overview
b) Resource utilization
c) Order list
d) Production list
09. To trigger a goods receipt posting, which Kanban status do you have to set?
Please choose the correct answer.
a) In use
b) Wait
c) Empty
d) Full
10. Which transaction code can you use in SAP S/4HANA to enter and display goods movements?
Please choose the correct answer.
a) MB02
b) MBNL
c) MIGO
d) MMBE
Quick Tips:
-
SAP provides a note "There are 'N' correct answers to this question." in actual SAP S/4HANA Production Planning and Manufacturing Certification Exam.
-
SAP does not ask "True or False" type questions in actual SAP C_TS422_2021, C_TS422_2020 Exam.
-
SAP provides an option to Increase (+) or Decrease (-) font size of exam screen for better readability in actual SAP S/4HANA Production Planning and Manufacturing Certification Exam.
Solutions:
QUESTION: 01
Answer: b |
QUESTION: 02
Answer: a |
QUESTION: 03
Answer: a, b |
QUESTION: 04
Answer: d |
QUESTION: 05
Answer: a, b |
QUESTION: 06
Answer: b, c, d |
QUESTION: 07
Answer: a, b, c |
QUESTION: 08
Answer: b, c |
QUESTION: 09
Answer: d |
QUESTION: 10
Answer: c |