SAP PP Certification Sample Question Set - 1

C_TSCM42_67 Dumps Free, C_TSCM42_67 PDF Download, SAP PP Dumps Free, SAP PP PDF Download, SAP Production Planning and Manufacturing Certification, C_TSCM42_67 Free DownloadThe SAP PP Certification Sample Question Set is prepared to make you familiar with actual SAP C_TSCM42_67 exam question format and exam pattern. To get familiar with more exam properties, we suggest you to try our Sample SAP PP Certification Practice Exam.

This Sample SAP PP Certification Practice Exam is designed for evaluation purpose only. If you are planning to write the SAP Production Planning and Manufacturing Certification Exam (C_TSCM42_67) and really want to test your SAP PP subject knowledge to identify your weak areas, we strongly recommend you to start your preparation with our Premium SAP PP Certification Practice Exam.

SAP PP Sample Questions:

01. Which objects can affect the calculation of capacity requirements for an operation?
Note: There are 3 correct answers to this question.

a) Standard values (routing)  
b) In-house production time (material master)  
c) Transport time (routing)  
d) Formulas (work center)  
e) Operation control key (routing)

02. A user of the SAP ECC system wants a rolling planning time fence (firming type = 1) to be set up for a material; in other words, new planned orders are firmed within a planning time fence. When an unforeseen production failure occurs, it can happen that such firmed planned orders are not being processed because time passes. What solution would automatically delete firmed planned orders?
Note: Please choose the correct answer.
a) In the material master, an MRP type is used in which the roll-forward mechanism is activated (Customizing for requirements planning).
b) The demand adjustment activated in the Customizing for demand adjustment is used.
c) Firmed planned orders can only ever be deleted manually because of the header data firming.

03. In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type Pd) The number in each of these alternatives represents a firming type.  
What does a firming type define?
Note: There are 2 correct answers to this question.
a) Handling existing procurement proposals outside the planning time fence.  
b) Handling existing procurement proposals within a planning time fence.  
c) Handling new requirements within the planning time fence.  
d) Handling new procurement proposals that need to be created due to new requirements within the planning time fence.

04. What options does the SAP ECC system offer to retrieve the available capacity for work centers?
Note: There are 3 correct answers to this question.
a) Attendance list
b) Standard available capacity
c) Shift plan
d) Interval of available capacity
e) Shift sequence

05. Which of the following master data can be used with process orders?
Note: There are 3 correct answers to this question.
a) Serial numbers  
b) Master recipes  
c) Resources  
d) Production/resource tools  
e) Production versions  

06. Which of the following organizational units does the manufacturing, planning, and execution process use?
Note: There are 2 correct answers to this question.
a) Storage Location
b) Sales Area
c) Purchase Organization
d) Plant

07. You want to enhance the system statuses of a production order with user statuses. How do you do this?
Note: Please choose the correct answer.
a) Define the user statuses in the order type-dependent parameters.  
b) Define a status profile in Customizing and assign it to the production scheduling profile.  
c) Define a status profile in Customizing and assign it to the order type.  
d) Define the user statuses in the Customizing table of the system statuses.  

08. You enter a new BOM (Bill of Materials) in SAP ECC but forget to enter a plant reference. Which of the following statements describes what happens when you try to save it?
Note: Please choose the correct answer.
a) When saving the BOM, a group BOM is created which can, under certain conditions, be assigned to a plant later.
b) When saving the BOM, a dialog box appears prompting the user to enter a plant.
c) When saving the BOM, an error message appears stating that it is not possible to save a BOM without a plant reference.
d) When saving the BOM, a warning message appears. In the corresponding dialog box, it is possible to create a plant-specific engineering BOM.

09. You want to use the different options for planning in SAP ECC. What is the correct sequence of the planning procedures?
Note: Please choose the correct answer.
a) Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planning  
b) Demand management -> Sales and operations planning -> Capacity planning -> Long-term planning -> Material requirements planning  
c) Material requirements planning -> Demand management -> Sales and operations planning -> Long-term planning -> Capacity planning  
d) Long-term planning -> Sales and operations planning -> Demand management -> Material requirements planning -> Capacity planning  

10. In the SAP ECC system, you interpret the result of a routing schedule. When scheduling a routing in the SAP ECC system which of the following time elements are interoperation times?
Note: There are 2 correct answers to this question.
a) Safety time
b) Floats before and after production
c) Processing time
d) Move time

Quick Tips:
  • SAP provides a note "There are 'N' correct answers to this question." in actual SAP PP Certification Exam.
  • SAP does not ask "True or False" type questions in actual SAP C_TSCM42_67 Exam.
  • SAP provides an option to Increase (+) or Decrease (-) font size of exam screen for better readability in actual SAP Production Planning and Manufacturing Certification Exam.

Solutions:

QUESTION: 01 Answer: a, d, e QUESTION: 02 Answer: a QUESTION: 03 Answer: b, d QUESTION: 04 Answer: b, d, e QUESTION: 05 Answer: b, c, e
QUESTION: 06 Answer: a, d QUESTION: 07 Answer: c QUESTION: 08 Answer: a QUESTION: 09 Answer: a QUESTION: 10 Answer: b, d

Note: If you find any typo or data entry error in these SAP Production Planning and Manufacturing (PP) sample questions, we request you to update us by write an email on feedback@erpprep.com.