Get C_TS412_2021 Dumps Free, and SAP S/4HANA Project Systems PDF Download for your SAP S/4HANA Project Systems Certification. Access C_TS412_2021 Free PDF Download to enhance your exam preparation.The SAP S/4HANA Project Systems Certification Sample Question Set on this page is designed to familiarize you with the actual SAP C_TS412_2021 exam format and question types. These basic sample questions help you understand the structure of the test and what to expect. While these questions provide a good starting point, they are just a glimpse of the real exam scenario. To get familiar with more exam properties, we suggest you try our Sample SAP S/4HANA Project Systems Certification Practice Test.

This Sample SAP C_TS412_2021 Certification Practice Exam is intended for evaluation purposes only. If you are planning to take the SAP Certified Associate - SAP S/4HANA Project Systems and want to thoroughly test your SAP S/4HANA knowledge to identify any weak areas, we strongly recommend starting your preparation with our Premium SAP S/4HANA Project Systems Certification Practice Exam. Our premium practice tests offer an extensive set of scenario-based questions that closely simulate the actual exam environment. By using our premium SAP S/4HANA Project Systems exams, you can ensure comprehensive coverage of all necessary topics, significantly boosting your confidence and increasing your chances of success on your certification exam.

SAP S/4HANA Project Systems Sample Questions:

01. When using budgeting and active availability control, which business transactions affect the current budget?
There are 3 correct answers to this question.
a) Cost element planning
b) Original budget
c) Revenues
d) Transfers
e) Supplements
 
02. You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?
Please choose the correct answer.
a) The control key is set to no scheduling.
b) The scheduling type is set to capacity requirements only.
c) The normal duration of each activity is missing.
d) There is a loop in the network.
 
03. How can material components be assigned to network activities?
There are 3 correct answers to this question.
a) Using manual assignment.
b) Using the bill of materials transfer.
c) Using assigned sales orders.
d) Using Project-Oriented Procurement (ProMan).
e) Using the Internet-based catalog.
 
04. You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined.
What are the possible reasons for this?
There are 3 correct answers to this question.
a) A work center has not been assigned to the activity.
b) The work center does not contain any available capacity data.
c) The wrong activity type category is entered in the activity.
d) The indicator that calculates capacity requirements is deactivated in the header of the network.
e) The capacity distribution key field is empty.
 
05. You want to confirm working hours to a WBS element using SAP Cross Application Time Sheet (SAP CATS). However, once you enter the WBS element and the working hours in SAP CATS you receive an error message. What could be the reason?
Please choose the correct answer.
a) The system status "created" is active.
b) The system status "master data locked" is active.
c) You are not the responsible person for that WBS element.
d) The confirmation exceeds the budget assigned to the WBS element.
 
06. What is copied when transferring a simulation version back to an operative project?
There are 3 correct answers to this question.
a) Plan costs
b) WBS elements
c) Actual work
d) Maintenance orders assigned to the project
e) Network activities
 
07. You want to extrapolate basic dates from lower to higher-level WBS elements. The duration of higher-level elements should NOT be reduced. Which planning method do you choose?
Please choose the correct answer.
a) Bottom-up
b) Strict bottom-up
c) Free planning
d) Top-down
 
08. You have implemented automatic requirements grouping for projects. Once you check the materials cabin and fork you realize that the requirements are grouped for cabin but not for fork.
What might be the reason?
Please choose the correct answer.
a) The grouping indicator of the top WBS element is set to a single MRP Group.
b) The network is set to no grouping for specific MRP Groups.
c) The MRP Group for fork is deactivated for grouping.
d) The project definition is set to no project stock.
 
09. You want to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you need to configure?
There are 2 correct answers to this question.
a) Define Layout Detail Screen for the WBS element to specify customer-specific tabs.
b) Define Create User-Defined Fields for the WBS element to specify the mandatory fields.
c) Define Field Selection for the WBS element to specify the mandatory fields.
d) Define Table Settings for the WBS element to specify customer-specific tabs.
 
10. Most of the reports in SAP Project System can be refreshed without exiting or closing the report. Which report must be restarted to update the displayed data?
Please choose the correct answer.
a) Hierarchical Reports
b) Individual Overviews
c) Reports by Cost Element
d) Structure Overview
 

Quick Tips:

  • SAP includes a note: "There are 'N' correct answers to this question" in the actual SAP S/4HANA PS Certification Exam.
  • SAP does not ask "True or False" type questions in the actual SAP C_TS412_2021 Exam.
  • SAP provides an option to increase (+) or decrease (-) the font size of the test screen for better readability in the actual SAP Certified Associate - SAP S/4HANA Project Systems Exam.

Solutions:

Question: 01

Answer: b, d, e

Question: 02

Answer: b

Question: 03

Answer: a, b, e

Question: 04

Answer: a, b, d

Question: 05

Answer: a

Question: 06

Answer: a, b, e

Question: 07

Answer: a

Question: 08

Answer: c

Question: 09

Answer: a, c

Question: 10

Answer: a